Construction
South Dhahran Home Ownership (SDHO) Inc. II Construction Access Road (AJYAL 2)
South Dhahran Home Ownership (SDHO) Inc. II Construction Access Road (AJYAL 2)
Scope of work:
The work consists of substantial earthworks including excavation, removal, and disposal of unsuitable materials, removal & relocation of existing fences, cut and fill and compaction using Rabid Impact Compaction works and overall grading, asphalting of temporary and permanent access roads and connecting roads, installation with complete testing and commissioning of Access Road Traffic signalization, street lighting, thrust boring, box culverts, and the stormwater system as follows:
- 2,750,000 Mᶟ Imported fill
- Commercial Access Road with length of 7.1 Km and 60 M width
- Intersection & Connecting roads: 3.2 km
- Type of Soil: Loose Sand with the very high water table
- Major dewatering works included managing the high volume of water encountered
- Major stormwater drainage scope is as follows:
- 800 linear meter length of underground concrete 4 cell box culverts with a total width of 12 meters
- 5 KM with 3 M diameter GRP storm drainage pipeline network
- 2 major crossing of live SWCC water line and live gas pipeline
- It includes also the crossing of 2 major high voltage overhead transmission lines. The major crossing starts with a 10-meter depth launching shaft and ends before the pipeline and ends with an 8-meter-deep receiving shaft and stormwater discharge culvert with a wing wall on the seashore line.
- Electrical Works, MV & LV cable Network for Street lighting including installing the lighting system.
- Traffic Signal Works
- Ancillary Works
-
Project status :30 months
-
Project Duration :Completed
-
Project site :Dhahran
-
Client name :Saudi Aramco
-
project name :Preparation of the general site for the housing of South Dhahran 2 (generations 2)
Related Articles
- Dammam South Housing - site preparation and infrastructure project
- Project for the construction of the laboratory building at the College of Petroleum Engineering and Geosciences at King Fahd University of Petroleum and Minerals
- Public site development project for the Innovation Center
- Crash Rated Fence at Vital Facilities project
- Project for the construction of supporting industrial facilities - Jazan Refinery
- Home Ownership Site Preparation, South Dhahran (AJYAL 1)
- Expand Dhahran Residential Community –Utility infrastructure and Networks Package 2
- Expand Dhahran Residential Community Package 1 (Facilities, infrastructure and networks)
- An excavation project for the historic shield gate - West Side
- Construction and Detailed Engineering Design Contract for the Laboratories Building of the College of Petroleum Engineering & Geosciences in KFUPM
- The construction of Saudi Arabian Agricultural Bank
- Implementation of development and development work in the centre of Al-Awamiya in Qatif province
- The construction of Al-Khobar Residential Complex - Third Stage - Part A
- The construction of three train stations in (Dammam, Hofuf, Riyadh)
- The construction of Internal Security Forces Hospital - MINISTRY OF INTERIOR